Two miles of West 20th Street, from Schifferdecker Road to Central City Road, used to be a two-lane road with open ditches on both sides. Now it has a center turn lane, curb and gutter, a storm sewer under the pavement, a 10-foot multi-use path alongside, and roundabouts at both Country Club Drive and Central City Road.
Drivers have been able to use the whole stretch without a detour since late September. The city's official celebration comes on Friday, Oct. 23. That date is not really the end of anything. The 20th Street rebuild belongs to a group of city projects that Joplin funded all at once rather than one at a time, and over the next year that group's construction moves elsewhere in town.
What's Out There Now
If you haven't driven the west end since the barricades came down, here's what changed:
- Lanes. Three lanes, one in each direction plus a center turn lane, replace the old two-lane road.
- Drainage. The bid called for about 10,000 linear feet of storm sewer and 110 inlets to replace the open ditches.
- Walking and biking. A parallel 10-foot multi-use path for people on foot and on bikes, which the City's notice also refers to as sidewalks.
- Intersections. Roundabouts at Country Club Drive, which is Black Cat Road on the other side, and at Central City Road.
Jeremy Hagerman, Joplin's assistant public works director, summed up the change for KSNF/KODE as the final asphalt went down:
"It went from being just a simple two-lane street to now we have three lanes, a walking path, a multi-purpose path, a roundabout at Black Cat, also known as Country Club Road, and a roundabout out at 20th Street, or at Central City Road."
The sources we reviewed don't give a posted speed limit for the finished road, and we didn't find any city guidance on using the two roundabouts. Watch the signs the first few times you drive through.
About Eighteen Months of Detours, in Order
West-side drivers have rerouted around this project since spring 2025. Here's how the closures went:
- April 7, 2025. The first phase closed 20th Street to through traffic between Iron Gates Road and Country Club Drive. Residents inside the closure could only get in from the east end.
- Through the rest of construction. The corridor was later closed to through traffic in stretches, with local access kept open for homeowners, emergency vehicles and service trucks. KOAM reported that the 20th and Country Club intersection reopened after water-main work while the section west of it stayed closed.
- July 6, 2026. The City closed the Central City Road intersection to through traffic for about two months. The detour used 32nd Street, Malang Road, West Junge Boulevard and Schifferdecker Avenue.
- Late September 2026. The final asphalt went down. By Sept. 30, KSNF/KODE reported that drivers could use the new pavement without a detour and that the project was wrapping up sooner than expected. Final touches and cleanup were expected to continue through October.
The Ribbon Cutting at Hole No. 3
The City of Joplin and the Joplin Area Chamber of Commerce will hold the ribbon cutting at 10 a.m. Friday, Oct. 23, near the entrance to Twin Hills Country Club at 2019 S. Country Club Drive. The event will be at hole No. 3. City Manager Nick Edwards, Mayor Rob O'Brian and Public Works Director Dan Johnson are scheduled to speak. The event is open to the community, and the City's announcement lists Cassie Faucett as the contact.
You may see two different prices for this project. The City's Oct. 12 event notice calls it a $14 million project. The City's earlier release in Joplin Business Outlook and the September construction coverage both use $9.8 million and name Emery Sapp and Sons, Inc. as the contractor. None of the sources we reviewed explains the difference. The funding mix is clearer. Money came from the capital improvement sales tax that voters passed in 2014 and renewed in 2024, with help from the City, Jasper County, the American Rescue Plan Act and the Joplin Special Road District.
Why So Much Is Finishing at Once
The ARPA line in that funding list helps explain why several Joplin projects are finishing around the same time.
City officials said on Oct. 9 that Joplin applied for more than 50 grants over three years and won 26 of them, bringing in nearly $58 million in federal money. With nearly $34 million in local matching funds, the approved projects add up to $97.3 million. The city estimates that raising the same amount through its capital improvement sales tax alone would have taken about 12 years.
That 12-year figure is why the road work has felt nonstop lately. The city's list of finished or nearly finished projects includes the widenings of 20th Street and Zora Street, eight stormwater projects, drinking water extensions, and upgrades to the emergency communications system. Projects that might once have been spread across more than a decade were scheduled close together. West 20th happens to be the first one with a ribbon cutting on the calendar.
What the New Path Reaches Today
The 10-foot path on 20th Street is new, and it's easy to assume it ties into the trail system around Shoal Creek. None of the city notices, bid documents or news stories we reviewed says that it does. None of them describes a link to Schifferdecker Park, the Tin Cup Trail or the Frisco Trail. For now, the documented path runs along 20th between Schifferdecker and Central City.
The nearest trail work is on the Shoal Creek side of town. The Tin Cup Trail opened in August 2025 as a 1.5-mile route between the St. John's Trail near Mercy Park and the trails in McIndoe Park. Its north start is just north of the Joplin Family Y at 32nd Street and McIntosh Circle. Its south entrance is on the west side of McIndoe Park along Glendale Road. When Tin Cup opened, its suspension bridge was still unfinished. The City's Oct. 9, 2026 project update now lists the Tin Cup Bridge and Trail as completed.
The Grand Falls Trail and Overlook Plaza is the piece meant to connect Tin Cup to the falls. As KSNF/KODE described it in March, the plans call for a 1.1-mile path along Shoal Creek, an overlook with nearly 1,000 feet of elevated boardwalk through the wetlands near the falls, and a parking lot, restroom, pavilion and trail signs. The parking lot, restroom and pavilion are planned for the east side of Riverside Drive. The project is a partnership with Missouri American Water. The trail is funded by a $600,000 Transportation Alternatives Program grant from the Missouri Department of Transportation, and the Parks and Stormwater Sales Tax covers the rest of the project.
Crews cleared trees last winter because the rules only allow removing habitat trees between Nov. 15 and March 15, which protects endangered bats in the area. As of the City's Oct. 9 update, the trail is still listed as in progress. We haven't found an opening date.
Where the Construction Moves Next
With 20th Street finished, here's where the rest of the list stood in early October:
| Project | Where | Status as of Oct. 2026 |
|---|---|---|
| Zora Street widening | Range Line Road to nearly I-49 | "Nearing Completion" in the City's Oct. 9 update |
| Zora Street final phase | Range Line Road to Duquesne Road | Gas line relocation underway to prepare |
| Grand Falls Trail | Shoal Creek, connecting to Tin Cup Trail | In progress |
| Parr Hill Park improvements | Parr Hill Park | In progress |
| Citywide broadband | Citywide | In progress |
| Main Street streetscaping, final phase | Main Street, 8th to 15th streets | Preparing to begin |
The parks work will also reach places west-side residents already go. A recreational trails grant will put 80 benches, plus trail signs, bike racks and tire repair stations, in 12 Joplin parks.
Main Street is the next project to watch. The $5 million final phase will add new sidewalks, decorative concrete, benches and trees between Eighth and 15th streets, linking the finished work downtown with the finished work in Southtown. Newstalk KZRG reported that city officials will hold a public meeting in the next several weeks where residents can review the plans and ask questions.
If you live off West 20th or are thinking about selling a home somewhere along Joplin's newly rebuilt corridors, we're glad to talk about how these changes look from your street. Show-Me Real Estate is a family-run, local office, and we follow these projects the same way you do, one detour at a time. Schedule a Free Consultation whenever you're ready.